User Story: As homeowner/project manager I want to have the walls plastered Sat 16/09 (Sean) so I can progress with plumbing
Closed this issue · 2 comments
DeeMcCart commented
EPIC: GENERAL
As a role I can capability so that received benefit
Assumptions:
Stud walls done
Acceptance Criteria
Sittingroom space for new socket with wiring through stud wall
Sittingroom fully plasterboarded and plastered
Hallway fully plasterboarded and plastered
Kitchen fully plasterboarded and plastered
(Note there is a follow-on task to replace the doors - later - after drying)
Furniture replaced in room - spaced from wall to allow drying space
Tasks
- Bolands - buy 1 sheet plasterboard; scrim and skimcoat x 3 bags (Deirdre)
- Brennans - buy 6m 2.5 something and earth cable (Deirdre)
- Wire between junction and socket (Sean)
- remove double doors, kitchen and sittingroom doors (Sean)
- finish plasterboarding in sitting room' (Sean)
- plaster sitting room (both walls) (Sean)
- finish plasterboarding in hall (Sean)
- plaster hall (Sean)
- finish plasterboarding in kitchen (Sean)
- plaster kitchen (Sean)
- Cleanup (Seanm then Deirdre)
- Replace furniture in room (Deirdre)
- 3 days drying (mother nature)
DeeMcCart commented
All done 16/09/23. Note follow-on tasks
DeeMcCart commented
Completed (picutres to follow)