'Add performance' not available at work level if work has multiple versions
Closed this issue · 1 comments
axgeertinger commented
Currently, performances cannot be added at work level if the work has more than one version. Until we have fixed this there are two workarounds:
- If possible, enter performance data before creating the second version of the work. Once there is at least one performance at work level it is possible to add more performances later.
- If versions are created already: Enter the performance data under one of the versions, save it, and use the perfromance's 'Move to...' option to move it to 'Work (no specific version)'.
axgeertinger commented
fixed