Can we add a milestone type?

shiaohuihoh opened this issue · 3 comments

Hi,

I would like to check if we can add a milestone type to the gantt chart?
Or can we take away the timeline for project task?
I've changed the duration to 0, but it auto-populate a value to the duration in the chart.

Thank you in advance.

Hi,

unfortunately milestones are only available in the PRO version. See the docs here and here.

I already stated this in the project README:

  • Based on dhtmlxGantt (docs) library (v4.1.0, newer version available from the vendor)
    • This is the GPLv2 version of the library with a reduced set of functions
    • If you need all functionality you can buy the Pro version and copy the Pro files into the plugin
    • I was asked to create this plugin and I have nothing to do with the company DHTMLX, so please do not complain ;-)

For the second question: Can you please give more details? A screenshot what you have currently and what you want to achive? Some sample data or a copy of the demo app with a running page showing your problem on apex.oracle.com?

Thank you and best regards
Ottmar

Close issue because no feedback since April.