phetsims/neuron

Neuron Master Checklist

Closed this issue · 3 comments

Note
Some of the usual checklist items have been removed as they were not applicable in this case. A third party (Ghent) paid for this sim to be developed so there was not the normal quoting process, and a simple quick mockup was sent as a guide

Design

  • Design doc created (Date: 03/15/2016)
  • Legacy sim docs/info gathered
  • Learning goals and standards identified (Date: 09/01/2014)
  • Design concept complete (Date: 09/01/2014)
  • Wireframes complete (Date: 09/01/2014)
  • Mockups complete (Date: 09/04/2014)
    • Mockups checked for colorblind and greyscale
  • Visual and interaction review of first deliverable
  • Interviews complete (Date: //)
    • Results reported to team
    • Notes pasted into design doc
    • Back-up of interviews
  • Lead designer "sign off" (Date: 02/09/2016)
    • Performance acceptable
    • Carefully review ?showPointerAreas
    • No new feature requests
  • Pre-publication items
    • Screenshot (2048x1344, PNG, 32-bit color, browser chrome stripped)
    • Accessories (keywords, categories, description, learning goals, related sims, NSDL)
    • Teacher guide
    • Compatible activities (author spreadsheet)
    • Update Gooru spreadsheet
    • Sim primer
    • Verify credits
  • Add to Edmodo

Implementation

  • Sim repo created (Date: 09/04/2014)
    • Collaborators added (such as 3rd party, QA team, designers, etc)
    • Standard label set applied
    • Sim added to active repos list in chipper
    • Sim suggestions doc reviewed
    • Unfuddle tickets reviewed
    • Port existing strings (IF ANY) and commit to the GitHub repo
  • Initial development started (Date: 09/10/2014)
  • Sim feature complete (Date: 01/28/2015)
  • Code review complete (Date: 12/20/2015)
    • Model description
  • PhET tweaks after sim acceptance (Date: 01/25/2016)
  • Published (Date: 02/29/2016)
    • Update repo README to published template

QA

  • Legacy sim tested for bugs; issues reported in repo
  • Dev testing complete (Date: 10/26/2015)
  • First release candidate (Date: 12/22/2015)
  • Sim accepted from third party (Date: 02/05/2015)
  • Test matrix deemed complete

Just primer left. Assigning to @amyh-phet

@ariel-phet Should be completed next week. Have recorded one version, gotten feedback from Stephanie, and just need to make a final recording.

@ariel-phet Checklist is complete. Closing