flowchart TD
A[A: 3.2] ----> B[B: 3.8];
A ----> C[C: 2.0];
B ----> D[D: 4.0];
C ----> E[E: 3.7];
C ----> F[F: 4.5];
E ----> G[G: 3.0];
D ----> H[H: 1.0];
G ----> H;
I[I: 3.7] ----> H;
F ----> I;
H ----> J[J: 2.2];
- Critical-Path:
A-C-F-I-H-J
- Slack-Path:
A-B-D-H-J
- If activity
E
crashes the critical path will not change. - If activity
F
crashes the new critical path becomesA-C-E-G-H-J
.