AMF-prototype-181209
First version of prototype for my Phd study
1
First update all the data using 'update' functions in all the modules: design, task, order, delivery, change_request information.
2
Then decide whether the construction material design are completed and are 'freezing'. Update and monitor the look ahead task planned start date and all the construction constraints.
Update/Input and control the forecasted material manufacturing lead time and transportation time. This will allow managers to know the estimated/latest date of 'release-for-manufacturing' and 'release-for-transportation'.
Update the 'Real time' of 'release-for-manufacturing' and 'release-for-transportation'
3
Tracking the material status everyday, which is affected the updated task date information, lead time, whether to freeze design.